The bathroom is coming along nicely.

The wall has been moved and the tub & toilet have now been installed. The tub surround is almost done, so we're just waiting for the sink and a bit of finishing in the room, plus a bit of fixup on the dining room ceiling since it was damaged when they replaced the old cast iron stack. I think it should be finished in a couple of days.
I have a sink & toilet in my basement and since I work at the Y, I can shower at work

so I'm doing ok here.
There was a delay of one day because the sidewalk crew poured the concrete and blocked them off from coming on Thursday (even though the guy I talked to assured me that wouldn't happen). But at least I have a wonderful sidewalk now.
Here is the sidewalk progression - 1st my gravel sidewalk.
next my gravel sidewalk with the steps that I just built.
then my new sidewalk with my new steps!